BlindPenguin Project

Project Time Table

penguin.gif


This time table is subject to dates being set for project handups.

Project Blind Penguin

154 days

10/05/99

05/05/00

Requirement Gathering and Refinement

11 days

10/05/99

10/19/99

Study Win 9X Systems

1 day

10/05/99

10/05/99

Research topic on Internet

2 days

10/05/99

10/06/99

Study other X Win screen magnification systems

5 days

10/05/99

10/11/99

Obtain info from library

1 day

10/12/99

10/12/99

Research user requirements

3 days

10/13/99

10/15/99

Document

2 days

10/18/99

10/19/99

Quick Design

6 days

10/20/99

10/27/99

Specify major functions

2 days

10/20/99

10/21/99

Draw up GUI

3 days

10/22/99

10/26/99

Document

1 day

10/27/99

10/27/99

Build Prototype

55 days

10/28/99

01/12/00

Build user interface

21 days

10/28/99

11/25/99

Get interface to interact with program

8 days

11/26/99

12/07/99

Document

4 days

12/08/99

12/13/99

Project Break for Christmas Exams

20 days

12/14/99

01/10/00

Hand up First Report

1 day

01/12/00

01/12/00

Evaluation

22 days

01/13/00

02/11/00

Design Tests

14 days

01/13/00

02/01/00

Implement Tests

7 days

02/02/00

02/10/00

Document

1 day

02/11/00

02/11/00

Refine Prototype

36 days

02/14/00

04/03/00

Review Test

4 days

02/14/00

02/17/00

Based on test, rewrite code

14 days

02/18/00

03/08/00

Document

3 days

03/09/00

03/13/00

Hand Up Second Report

1 day

03/14/00

03/14/00

Project Break for Easter Exams

14 days

03/15/00

04/03/00

Engineer Package

24 days

04/04/00

05/05/00

Review Tests

7 days

04/04/00

04/12/00

Build final package

13 days

04/13/00

05/01/00

Final Documentation/Hand up

4 days

05/02/00

05/05/00